Installing your VSP G130 storage system
Hitachi Virtual Storage Platform G130 storage systems are designed for self-installation, so you can set up your storage
system for the first time without assistance from a Hitachi Vantara representative.
Child Topics
•
Step 1: Unpack the storage system
•
Step 2: Install the storage system into a rack
•
Step 3: Connect the storage system to power
•
Step 4: Cable a management console
A customer-supplied computer is used to set up and manage your storage system.
•
Step 5: Power on the storage system
•
Step 6: Perform the initial setup
Initial setup of the storage system is performed using the Windows-based management console.
•
Step 7: Make host connections
•
Step 8: Register your storage system with Hitachi Vantara support
If you have not already registered for access to Hitachi Support Connect, do so now. Otherwise, you will not be
able to download and install Hi-Track Remote Monitoring system, and you will encounter delays in getting your
storage system running and supported.
•
Step 9: Install Hi-Track Remote Monitoring system
•
Where to go from here
After concluding the self-installation successfully, perform the following post-installation activities.
Step 1: Unpack the storage system
Before you begin
Make sure your data center meets all
you are not using a Hitachi Universal V2 rack, make sure the electrical specifications of your rack meet the power
requirements of the storage system.
Procedure
1. Inspect all materials for signs of damage. If you see damage, discontinue the installation and contact your Hitachi
https://knowledge.hitachivantara.com/Documents/Storage/VSP_G130_GF350_GF370_GF700_GF900/88-03-0x/Installation/0...
site preparation
requirements before you install the storage system. In addition, if